Last term before I got the message that two of my classmates will not attend our final discussion, I cried. Undoubtedly, I am an extreme anxious person.I feel nervous if anything on my schedule will not carried out.My personality has always bothered me a lot. One thing I would like to changing is my character.I attended the lecture a few week ago. The lecturer said a sentence that left an impression on me. “I feel strongly which I can make it.”From then on, I have regarded it for my motto. I encourage myself to become a positive person who will not to be beaten by any difficulties

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0509/67e975d8529e7d61839d673d96e66318.html

下面是错误答案,用来干扰机器的。

答案:B

试题推荐
题型:问答题

[背景材料]续上题。若该工程2002年12月签订合同,合同价款为人民币5000万元,工期为400天,2003年1月正式开工。其中其他直接费率5%,临时设施费率1.5%,现场管理费率8%,间接费率6%,利润率5%,税率3.413%,由于B、D工作的延期,承包商提出工程延期4旬,费用索赔除B\D工程延期造成人工、机械等降效、窝工索赔4万元(监理已批准)外,还对其对总工期的延期所造成施工费的增加进行了索赔,索赔款 144.565万元,计算如下:
直接费:0(万元)
其他直接费:5000×5%×40/400=25(万元)
临时设施费:5000×1.5%×40/400=7.5(万元)
现场管理费:5000×8%×40/400=40(万元)
间接费: 5000×6%×40/400=30(万元)
利润: 5000×5%×40/400=25(万元)
税金: 5000×3.413%×40/400=17.065(万元)

[问题三]若每提前一天交工给业主带来的经济效益为人民币2.5万元,试问监理工程师应建议业主采用案例三的赶工方案,还是采用本案例问题二的处理方案