A key activity in closing out a project is

题型:单项选择题

题目:

A key activity in closing out a project is to (47) .

A.Disseminate status reports and risk assessment.

B.Disseminate information to formalize project completion.

C.Monitor the specific project results to determine if they comply with relevant quality standards.

D.Transfer all the project records to the project owners.