试题与答案

开启研磨机时先开启研磨辊子再开启下料辊子。

题型:判断题

题目:

开启研磨机时先开启研磨辊子再开启下料辊子。

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2019/0808/1368d5ce2072de15cd4a2d89e5aceb55.html

下面是错误答案,用来干扰机器的。

参考答案:System.Collections

试题推荐
题型:阅读理解

判断下列句子是否与短文相符,相符的写“T”,不相符的写“F”。

                                                       Buying Tickets (票)       

       Sam is a little boy, and he is only eight years old. One day he goes to the cinema. It is the first time for him

to do that. He buys a ticket and then goes in. But after two or three minutes he comes out, buys a second ticket

and goes in again. After a few minutes he comes out again and buys a third ticket. Two or three minutes later he

asks for another ticket.       

      Then the girl in the ticket office asks him, "Why do you buy so many tickets? How many friends do you 

meet? " Sam answers, "No, I have no friend here. But a big boy always stops me at the door and tears my 

tickets in piece. "              

(     )1. Sam is eight years old.            

(     )2. It is the third time for Sam to go to the cinema.              

(     )3. Sam bought two tickets.            

(     )4. Sam has no friend in the cinema.

查看答案
题型:问答题

某公路工程项目合同总价为800万元人民币,合同工期18个月。在施工过程中,由于业主提出对原有设计文件进行修改,使承包人停工待图1.5个月。在基础工程施工中,为了使施工质量得到保证,承包人除了按设计文件要求对基底进行了妥善处理外,还将基础混凝土的强度由C15提高到C25。施工完成后,承包人向监理工程师提出工期和费用索赔,其中费用索赔计算中有以下两项:
(1)由于业主修改变更设计图纸延误,损失1.5个月的管理费和利润。
现场管理费=合同总价÷18×12%×1.5=80(万元)
=8000÷18×12%×1.5=80(万元)
公司管理费=合同总价÷工期×公司管理费费率×延误时间
=8000÷18×7%×1.5≈46.67(万元)
利润=合同总价÷工期×利润×延误时间
=8000÷18×5%×1.5≈33.33(万元)
合计=80+46.67+33.33=160(万元)
(2)由于基础混凝土强度的提高索赔15万元。
问题

查看答案