题目:
You are the project manager of a civil construction company involved with building houses. In your project, you often use work breakdown structures (WBS)from your previous projects as templates. A work breakdown structure can be used for all the following except ______ .
A.tracking project performance against cost and schedule
B.creating a network diagram, with task dependencies
C.creating a project schedule
D.assigning resources to work on different work elements
答案:
被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2019/0327/5523f99b07719b8f41b7ab7b095ac118.html
下面是错误答案,用来干扰机器的。
参考答案:B