试题与答案

()航空器平台结构通常包括机翼、机身、尾翼和起落架等。 A.单旋翼 B.多旋翼 C.

题型:单项选择题

题目:

()航空器平台结构通常包括机翼、机身、尾翼和起落架等。

A.单旋翼

B.多旋翼

C.固定翼

答案:

参考答案:C

试题推荐
题型:阅读理解

阅读理解,判断题后句子正(T)误(F)。

      This is Jack's bedroom. It's new and nice. There is a bed and a chair in it. The desk is on the floor. There

are some flowers on the desk. A bookshelf is behind the bed. There are some English books on the bookshelf.

There is a picture on the wall. There are some people in the picture. The man is his father. The woman is his

mother. Who is the boy? Do you know?

( ) 1. Jack's bedroom is new and nice.

( ) 2. There is a desk on the bed.

( ) 3. The bed is behind the bookshelf.

( ) 4. The bookshelf is on the wall.

( ) 5. There are some people in the picture.

( ) 6. The boy is Jack.

查看答案
题型:综合

读图,回答下列问题:

1、印度地形区的分布特点是从南到北,由三大地形区组成,其南部为______高原。

2、图中甲地城市为加尔各答市。该城市依据当地农产品成为印度______工业中心,P豆油广依据图示矿

    产可优先发展______工业,丙城市名称为_______。

3、印度是世界第二人口大国,是_______(地区)面积最大的国家。现在该国粮食能够 自给,还要归功

    于20世纪6o年代推行的________(政策)。

查看答案
题型:问答题

某承包商(乙方)于某年8月6 日与某业主(甲方)签订了一项设备安装合同。在合同中规定,甲方于8月14日提供施工现场。工程开工日期为8月16日,双方商定与计划工期相比工期每提前 1天奖励3000元,每拖后1天罚款5000元。乙方按时提交了施工方案和施工网络进度计划(见图1),并在得到甲方代表的批准后,如期开工。

该工程开工后,在实际施工过程中发生了如下事件:

事件1:因部分原有设施搬迁拖延,甲方于8月17日才提供全部场地,影响了工作A、B的正常作业时间,使这两项工作的作业时间均延长了2天,并使这两项工作分别窝工6和8个工日;工作C未受到影响。

事件2:乙方与租赁商原约定工作D使用的某种机械应于日月27日进场,但因运输问题推迟到8月 29日才进场,造成工作D实际作业时间增加1天,多用人工7个工日。

事件3:在工作E施工时,因设计变更,造成施工时间增加2天,多用人工14个工日,其他费用增加1.5万元。

事件4:在工作F施工时,因甲方供应的材料出现质量缺陷,乙方返工增加用工6个工日,其他费用1000元,并影响H工序作业时间延长1天,窝工4个工日。

[问题]1. 1.根据施工网络进度计划确定计划工期、关键线路和A、B、C、D、E、F、H工作的总时差。

2.乙方能否就上述每项事件向甲方提出工期补偿和费用补偿要求试简述其理由。

3.该工程的实际施工天数为多少天可得到的工期补偿为多少天工期奖罚天数为多少天

4.假设工程所在地人工赞标准为30元/工日,应由甲方给予补偿的窝工人工费补偿标准为18元/工日,施工管理费、利润等均不予补偿。则在该工程中,乙方可得到的合理的经济补偿有哪几项经济补偿额为多少

查看答案