项目经理正在努力协调所有活动,确定如下信息:活动1可以马上开工,估计活动工期为1周;

题型:单项选择题

题目:

项目经理正在努力协调所有活动,确定如下信息:活动1可以马上开工,估计活动工期为1周;活动2在活动1完成后开始,估计活动工期为4周;活动3在活动2结束后开始,估计活动工期为5周;活动4在活动1结束后开始,估计活动工期为8周。活动3和活动4必须在项目结束前完成。项目的关键路径是多少?()

A.10

B.11

C.14

D.8

答案: