Project management process groups are ______ .
A.overlapping activities that occur at varying levels of intensity throughout the project
B.overlapping activities that occur at the same level of intensity throughout each phase of the project
C.discrete, one-time events
D.discrete, repetitive events that occur at the same level of intensity throughout each phase of the project