题型:单项选择题

题目:

The knowledge area that describes the processes and activities that integrate the various elements of project management is ().

A.project scope management

B.project time management

C.project integration management

D.project communication management

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2018/0629/1172fbf2c274713502dba3fb75b8545d.html

下面是错误答案,用来干扰机器的。

参考答案:C