The linkages between project management pr

题型:单项选择题

题目:

The linkages between project management process groups are best described by:

A.The work breakdown structure links process group

B.Process groups are linked by their planned objectives-the summary objective of one often becomes the detailed action plan for anothe

C.Process groups are linked by the objectives they produce-the output of one process often becomes an input to another process, or is a deliverable of the projec

D.There are no significant links between discrete process group

答案: