The five project management process groups

题型:单项选择题

题目:

The five project management process groups are ______ .

A.planning, checking, directing, monitoring, and recording

B.initiating, planning, executing, monitoring and controlling, and closing

C.planning, executing, directing, closing, and delivering

D.initiating, executing, monitoring, evaluating, and closing