You have recently taken over a new project when the previous project manager resigned. While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, you should recommend ______ .
A) issuing budget updates
B) revising the cost baseline
C) corrective action e. g. adjusting schedule activity budgets
D) closing the project