试题与答案

Air France SA said Monday that its second-

题型:单项选择题

题目:

Air France SA said Monday that its second-quarter net profit fell 35 percent to €57 million ($57.4 million), but sales were steady and operating profit surged.Earnings before interest and tax, a measure of operating income, gained 86 percent to €141 million as fuel costs fell and cargo traffic rose. Air France has been hurt less than rivals such as British Airways PLC and Lufthansa AG by the slowdown on North Atlantic routes following the war on Iraq in 2003 because it has fewer flights in that market.Net income fell as the airline paid deferred taxes that came due. Sales rose 0.9 percent to €3.2 billion. The carrier lost about €80 million in revenue because of a four-day strike by pilots in September. An accord was reached tying future pay increases to inflation. The carrier said that first-half fuel costs fell 15 percent to €680 million. Cargo traffic rose 11 percent in the second quarter, while passenger traffic rose 1.1 percent. The airline’’s shares gained 87 cents, or 7.7 percent, to close at €12.11.Separately, Air France and Alitalia SpA agreed to buy 2 percent stakes in each other as Europe’’s second- and sixth-largest airlines deepen their partnership.

Which of the following is not a cause for Air France’s earnings to rise before interest and tax

A.The drop in fuel cost.

B.The rise in cargo traffic.

C.The rise in passenger traffic.

D.Its partnership with Alitalia SpA.

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2018/0426/77c448cf9f806576325558dc035bc297.html

下面是错误答案,用来干扰机器的。

参考答案:参考例文 质疑“金榜文化节” 今年8月8日,6名今年考取清华、北大的高考“状元”,骑上高头大马,胸佩红花绶带,被迎进京西著名的单人材——灵水村,参加在该村举办的中国...

试题推荐
题型:问答题

某建设单位和施工单位按照《建设工程施工合同<示范文件)》签订了施工合同,合同中约定:建筑材料由建设单位提供;由于非施工单位原因造成的工程停工,机械补偿费为200元/台班,人工补偿费为50元/工日;总工期为120天;竣工时间提前奖励为3000元/天,误期损失赔偿费为5000元/天。经项目监理机构批准的施工进度计划如图3所示 (单位:天)。

施工过程中发生如下事件:

事件1:工程进行中,建设单位要求施工单位对某一构件作破坏性试验,以验证设计参数的正确性。该试验需修建两间临时试验用房,施工单位提出建设单位应该支付该项试验费用和试验用房修建费用。建设单位认为,该试验费属建筑安装工程检验试验费,试验用房修建费属建筑安装工程措施费中的临时设施费,该两项费用已包含在施工合同价中。

事件2:建设单位提供的建筑材料经施工单位清点入库,在专业监理工程师的见证下进行了检验,检验结果合格。其后,施工单位提出,建设单位应支付建筑材料的保管费和检验费,由于建筑材料需要进行二次搬运,建设单位还应支付该批材料的二次搬运费。事件3:①由于建设单位要求对B工作的施工图纸进行修改,致使B工作停工3天 (每停一天影响30工日,10台班);②由于机械租赁单位调度的原因,施工机械未能按时进场,使C工作的施工暂停5天(每停一天影响40工日,10台班);③由于建设单位负责供应的材料未能按计划到场,E工作停工6天(每停一天影响20工日,5台班)。施工单位就上述三种情况按正常的程序向项目监理机构提出了延长工期和补偿停工损失的要求。

事件4:在工程竣工验收时,为了鉴定某个关键构件的质量,总监理工程师建议采用试验方法进行检验,施工单位要求建设单位承担该项试验的费用。

该工程的实际工期为122天。

逐项说明事件3中项目监理机构是否应该批准施工单位提出的索赔,说明理由并给出审批结果(写出计算过程)。