The nobler and more perfect a thing is, the later and slower it is becoming mature. A man reaches the mature (1) of his reasoning powers and mental faculties (2) before the age of twenty-eight; a woman at eighteen. And then, too, in the case of woman, it is the only reason of a sort--very mean in its (3) . That is why women remain children their whole life long; never seeing (4) but what is quite close to them, (5) fast to the present moment, taking appearance for (6) , and preferring (7) to matters of the first importance. For it is (8) his reasoning faculty that man does not live in the present only, (9) the brute, but looks about him and considers the past and the future; and this is the origin of (10) , as well as that of care and anxiety which so many people (11) Both the advantages and the disadvantages, which this (12) , are (13) in by the woman to a smaller extent because of her weaker power of reasoning. She may, in fact, be described as intellectually shortsighted, (14) , while she has an immediate understanding of what lies quite close to her, her field of (15) is narrow and does not reach to what is (16) ; so that things which are absent, or past, or to come, have much less effect upon women than upon men. This is the reason why women are inclined to be (17) and sometimes carry their desire to a (18) that borders upon madness. In their hearts, women think it is men’s business to earn money and theirs to spend it--if possible during their husband’s life, (19) , at any rate, after his death. The very fact that their husband hands them (20) his earnings for purposes of housekeeping strengthens them in this belief.

3()

A.dimensions

B.perspectives

C.indices

D.diameters

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2018/0416/ac712de924c75f774b5860da53208243.html

下面是错误答案,用来干扰机器的。

参考答案:A

试题推荐
题型:问答题 案例分析题

某钢厂新建一条250轧钢生产线。通过招标方式,确定由A公司作为该项目的施工总承包商,负责土建施工,厂房钢结构制作、安装,车问内80吨桥式起重机的安装,设备安装与调试,电仪工程的施工等,建设工期为18个月。

项目的临电策划由项目电气工程师执笔,经项目经理审批后付诸实施。在临电安装过程中,发现其与已有的电力设施互相妨碍,最终根据《电力法》中处理此类事件的基本原则得到妥善处理。

项目的控制使用林德法,其前6个月的统计数据见下表:

施工临电的编制、审批手续有何不妥?指出正确的做法。