项目的渐进明细通常与哪个过程组有最密切的关系( )A.启动B.规划C.执行D.监控

题型:单项选择题

题目:

项目的渐进明细通常与哪个过程组有最密切的关系( )

A.启动
B.规划
C.执行
D.监控

答案:

参考答案:B

解析:[考点与答题技巧] 在规划过程组中,需要不断地对项目计划进行渐进明细。渐进明细通常用滚动式规划的方法来实现。

试题推荐
题型:阅读理解

Sydney Tower
Address: 100 Market St., Sydney
Phone: 02 9333 9222
Fax: 02 9333 9203
Open time: 9:00 a.m. to 10:30 p.m. (Saturdays to 11:30 p.m.)
Ticket: $60 (for an adult)
$30 (for a child)
Website: www.sydneytower.com.au
How to get there: train to Town Hall Station and a short walk along Market
Street
How to book tickets: by phone/fax or through the web
Attraction: Sydney’s best views are just the beginning! Sydney Tower takes you to the highest point above Sydney for exciting 360 views of our beautiful city.
 
小题1:   Sydney Tower is ________ in Sydney, Australia.
A.the busiest streetB.the biggest station
C.the most beautiful parkD.the highest point
小题2:   If you want to book a ticket to Sydney Tower, you can’t ________.
A.email sydneytower@hotmail .com
B.fax 02 9333 9203
C.search www. sydneytower.com.au
D.dial 02 9333 9222
小题3:   Frank wants to go to Sydney Tower with his two children, he will pay _________.
A.$60B.$90C.$120D.$150
小题4:   Last Saturday, Johnson went to visit Sydney Tower. He had to get down the tower __________.
A.after 11:30 p.m.B.before 11:30 p.m.
C.at 10:30 p.m.D.by 10:30 p.m.
小题5:   The passage above is probably___________.
A.a piece of newsB.a conversation
C.a storyD.an advertisement
查看答案
微信公众账号搜索答案