If Task C has 0 days of free float and 0 d

题型:单项选择题

题目:

If Task C has 0 days of free float and 0 days of total float, what does this mean to the project

A) The project does not have adequate lead and lag times built in.
B) The task is on the critical path.
C) The duration of the task should be compressed.
D) The dates for the task are not accurate.

答案: