A project was expected to cost $6 million for 3 months. At the end of 1 month, you use earned value as a performance management tool and get the following information: BCWP=$1.5 million, BCWS=$2.5 million, ACWP=$2.2.million. What is the schedule variance ?()
A.$0.3 millio
B.$-1 millio
C.$1 million。
D.$0.7 millio