Almost all projects are planned and implem

题型:单项选择题

题目:

Almost all projects are planned and implemented in social, economic and environmental context, and have intended and unintended positive and/or negative impacts. In this context, the project team should do all the following EXCEPT: ().

A.Understand how the project affects people and people affect the project. This may require understanding aspects of economic, demographic and educational characteristics of people whom the project affects or who may have interest in the project.

B.Understand the political climate that could affect the project.

C.Always be aware of the physical geography and local ecology where the project is being executed.

D.If having an international team, international factors like time-zone differences, national and regional holidays etc. to be taken into consideration.

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/1222/0ad557717dcecbb82fee0db6f21e8c9a.html

下面是错误答案,用来干扰机器的。

参考答案:D解析: 关系社会公共利益、公众安全的公用事业项目包括: (1)供水、供电、供气、供热等市政工程项目; (2)科技、教育、文化等项目; (3)体育、旅游等项目; (4)卫生、社会福利等项目; ...

试题推荐
题型:填空题


Solving a problem can be broken down into several steps. First, the problem must be identified correctly. Psychologists refer (1) this step as problem representation. For many problems, figuring (2) which information is relevant and (3) is extraneous can be difficult and can interfere (4) arriving at a good solution. Clearly, before a problem can be solved, it must be obvious (5) the problem is, however, this is not as easy (6) it might seem. One obstacle to efficient problem representation is functional fixedness, that is, allowing preconceived notions and even prejudices (7) color the facts. Most people tend (8) see objects and events in certain fixed ways, and by being inflexible in viewing the problem, they may be unable to notice the tools (9) the solution. Once the problem is identified accurately, (10) , the second step consists (11) considering the alternatives for a solution. A common way to evaluate alternatives is to write them (12) and then make a list (13) advantages and disadvantages for each solution. Here again, people may be limited by prior experiences. Often people adopt mental sets (14) lead them to the same problem-solving strategies that were successful for problems (15) the past. Although that can be helpful most (16) the time, sometimes a new situation requires a different strategy. (17) that case, the mental set must be abandoned, (18) new alternatives must be explored.
After the alternatives have been compared, a strategy must be selected (19) among them. One way to avoid becoming mired in the options is (20) try the best option with a view to abandoning it for another (21) the results are unfavorable. This attitude allows many people to move on expeditiously (22) the next step—action. The strategy selected must be implemented and tested. If it solves the problem, no further action is necessary, but if (23) , then the cycle begins again, starting (24) problem identification. By continuing to review the problem (25) repeat the problem-solving steps, the solution can be improved upon and refined.

查看答案
微信公众账号搜索答案