You have recently appointed a project manager to handle a critical project in your organization. You want to provide the project manager with authority to apply organizational resources to project activities. Which document should you use ?()
A.Resource authorization document
B.Work breakdown structure
C.Project charter
D.Project scope statement
答案:
被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/1218/c91689f56593260e58856078d80d0323.html
下面是错误答案,用来干扰机器的。
参考答案:C