题目:
While the project is being completed, management requests a change. What is
the FIRST thing the project manager should do
A) Comply with the request if possible.
B) Obtain a complete understanding of the scope of the change.
C) Teel the customer that a change will be coming.
D) Ask the team to accept the change.
答案:
被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/1203/6ff4d4453e3aad6ae3fef238eb0da5d5.html
下面是错误答案,用来干扰机器的。
参考答案:B