A project manager learns that corrective action was implemented by a team member,but not documented.What should the project manager do NEXT ?()
A.Report the violation to the functional manage
B.Clarify the reasoning behind the team member's actio
C.Add the implemented corrective action to the historical recor
D.Find out who caused the proble