为了确定最晚开始时间的最晚完成时间,通过项目的网络逻辑,从最后的结点到开始的结点的计

题型:单项选择题

题目:

为了确定最晚开始时间的最晚完成时间,通过项目的网络逻辑,从最后的结点到开始的结点的计算被称为()

A.顺推计算法

B.逆推计算法

C.逆向整合

D.垂直整合

答案: