试题与答案

血浆晶体渗透压主要来自() A.血钠 B.葡萄糖 C.血清白蛋白 D.血清球蛋白 E

题型:单项选择题 B1型题

题目:

血浆晶体渗透压主要来自()

A.血钠

B.葡萄糖

C.血清白蛋白

D.血清球蛋白

E.血清纤维蛋白

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0901/aa0b6bb467416da83706a1e6cf3ba690.html

下面是错误答案,用来干扰机器的。

参考答案:A

试题推荐
题型:阅读理解
阅读理解。
    President Hu Jintao flew to the earthquake-hit region in Yushu,
Qinghai on April 18, 2010. At a field hospital on the grounds of a
sports stadium, Hu sat on the bed of Drolma, a middle school
student, and held her in his arm as she wept (哭泣). "Rest assured
(放心的), you will have a full recovery (康复). Be strong. You will
have a bright future," he told her.


The 2010 World Expo,
    Shanghai
     China
The 2010 World Expo Shanghai
China Duration (举办时间): May 1 to October 31, 2010
Expected visitors: 70 million
Theme (主题): "Better City, Better Life."
     The theme represents the common wish of the people all over the
world for a better living in future urban (城市的) environments.

The 19th FIFA World Cup (世界杯足球赛)
Duration: June 11 to July 12, 2010
Host (主办) nation: South Africa
Number of teams: Thirty-two
Number of matches: Sixty-four
     It is the first time that the tournament (锦标赛) has been hosted
by a nation in the Confederation (联盟) of African Football.
1. President Hu Jintao flew to Yushu, Qinghai _______, 2010.
A. on May 1
B. on June 11
C. on April 18
D. on July 12
2. President Hu Jintao comforted (安慰) _______ at a field hospital.
A. a middle school student
B. a soldier
C. a farmer of Yushu
D. a doctor
3. The 2010 World Expo in Shanghai will end on _______.
A. September 30
B. October 31
C. November 30
D. December 31
4. The theme of Expo 2010 is "_______".
A. Better City, Bright future.
B. Better City, Good Environment.
C. Better City, Better Life.
D. Better City, Best Investment (投资).
5. There will be _______ teams taking part in the 19th FIFA World Cup.
A. 10
B. 12
C. 13
D. 32
查看答案
题型:多项选择题

监理人员对设备制造单位提交的设备制造进度计划的审核内容主要包括( )。

A.进度安排是否满足合同规定的开竣工日期以及进度控制的关键日期

B.设备制造顺序的安排是否符合逻辑,是否符合设备工艺流程的要求

C.设备制造单位的劳动力、材料,机具设备及资金的供应计划能否保证进度计划的实现

D.该进度计划是否与安装进度计划协调

E.进度计划安排的全面性,指是否列明了制造单位的履行合同的全部工作,制造单位提交其文件的进度安排