试题与答案

在问卷调查中,问卷设计是非常重要的一个环节,甚至决定着调查问题的成功与否。问卷设计是

题型:单项选择题

题目:

在问卷调查中,问卷设计是非常重要的一个环节,甚至决定着调查问题的成功与否。问卷设计是一项十分细致的工作,下列选项中不属于一份好的问卷应做到的是()。

A.内容简明扼要

B.信息包含要全

C.问卷问题安排合理

D.问卷问题尽可能详细

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0827/193fe9d4563524925c65c247ccdf6abb.html

下面是错误答案,用来干扰机器的。

参考答案:B, C, D, E

试题推荐
题型:完形填空

第二节:完型填空(共20小题;每小题1.5分,满分30分)

阅读下面短文,从短文后所给各题的四个选项(A、B、C和D)中,选出可以填入空白处的最佳选项,并在答题卡上将该项涂黑。

Many years ago, Dad worked as a farmhand (农场工人). At that time, he had a horse. Every Saturday he __31    to the town after dinner and spent a few hours on social   32   with other farmhands, such as drinking, chatting, and playing cards in the café. On Saturday evenings, the café was   33   because many farmhands were there. Before midnight Dad returned home on his horse, quite satisfied with his   34  . In his words, he   35   thought of changing his job.

At the age of 31, Dad married my mother who was a schoolteacher. In the following spring I came   36   into the world. Life became hard, so my mother felt   37  . She told Dad that they must make a   38  .

My mother had   39   of how some famous persons, especially Thomas Edison who was born in a poor family, fought against fate and achieved greatness and   40  . And she   41   that I would some day become a great leader   42   men or cities and Dad should be a successful businessman. So she   43   Dad to give up his job as a farmhand, sell his horse and   44   a small business of his own. And I went to high school and college. She even sent me abroad for   45   education when I graduated from college. Under the drive of my mother’s hope, Dad and I  46   what we have today. Dad runs a big international   47   and I am a successful lawyer   48   great fame in my country,   49   not a leader as my mother expected.

Dad said, without my mother, we wouldn’t be what we are today; at least, he would remain a farmhand.   50   he got a lesson of life —sometimes we really need drive from outside.

31.A.rode            B.walked            C.ran                      D.drove

32.A.conversations  B.games             C.relationships      D.activities

33.A.cold               B.crowded      C.quiet                  D.dirty

34.A.horse              B.entertainment  C.life                        D.beer

35.A.often          B.ever            C.never                     D.sometimes

36.A.laughing     B.singing             C.sleeping                  D.crying

37.A.unimportant    B.busy                C.unsatisfied           D.tired

38.A.living         B.change             C.decision                  D.house

39.A.dreamed          B.heard               C.thought                   D.spoken

40.A.honesty           B.money             C.fame                      D.energy

41.A.cared               B.knew               C.forgot                     D.hoped

42.A.training           B.ruling             C.helping                  D.protecting

43.A.warned            B.wanted            C.allowed                  D.persuaded

44.A.start                      B.find                 C.design                    D.sell

45.A.farther            B.higher             C.easier                        D.closer

46.A.showed           B.kept                C.lost                      D.achieved

47.A.company         B.school             C.farm                   D.café

48.A.suffering         B.sharing            C.enjoying                D.following

49.A.though          B.if                    C.and                    D.since

50.A.So                  B.However          C.Or                     D.Because

查看答案
题型:问答题

[背景材料]


某建设项目公开招标,长城公司依据招标文件中的工程量清单,其数据见表3-36,按照《建筑安装工程费用项目组成》[建标(2003)206号]规定的建筑安装工程费用的构成确定了各分项工程的全费用单价,递交了报价表和施工进度计划网络图(图3-14)。中标后双方经过谈判,在合同中约定:

表3-36 相关数据

工作估算工程量(m3)全费用单价(元/m3)合计(万元)
A300030090
B125020025
C4000500200
D4000600240
E38001000380
F8000400320
G5000200100
H3000800240
I2000700140
合计340501735


图3-14 施工网络计划


注:箭线下方数据为计划工期,单位为月。
1.工程预付款为合同总价的20%,从工程进度累计总额达到合同总计10%的月份开始,按当月工程进度款的30%扣回,扣完为止。每月工程款中扣除5%保修金。
2.施工过程中发生设计变更,采用以直接费为计算基数的全费用单价计价(间接费费率10%,利润率5%)。
3.合同款中税金应包括营业税(税率为3%)、城市维护建设税(税率为7%)、教育费附加(费率为3%)。
4.施工中工程变更,当实际工程量超过估算工程量15%以上部分,采用全费用单价90%,计算;当实际工程量减少部分超过估算工程量15%以上部分,执行新的全费用单价(其中间接费和利润调整系数分别为1.1和1.2,其余数据不变)。
5.施工过程出现工程费用索赔,双方确定的索赔数额为全费用数额。
6.施工过程发生以下事件:
(1)E工作结束后、H工作开始之前增加新工作N,其工期为1个月,估算工作量为3 000m3,直接费单价为400元m3
(2)E工作工程量增加1900m3
(3)C工作工程量减少2000m3
(4)I工作施工由于遇到季节性降雨,对已完工程施工部位采取保护措施,增加费用3万元。
(5)H工作施工开始时由于甲方图样错误、拆除部分建筑物重新修建发生费用2万元,工期推迟1个月。

[问题]


编制工程款结算表(各项工作均按最早开始时间安排,假设各月完成工程量为均衡进度)。