Project schedule management is made up of

题型:单项选择题

题目:

Project schedule management is made up of six management processes including:activity definition,activity sequencing()and schedule control by order.

A.activity duration estimating,schedule developing,activity resource estimating

B.activity resource estimating,activity duration estimating,schedule development

C.schedule developing,activity resource estimating,activity duration estimating

D.activity resource estimating,schedule developing,activity duration estimating