试题与答案

在我们已学过的知识中,用来说明燃料优劣的物理量是______;天然气是_____

题型:填空题

题目:

在我们已学过的知识中,用来说明燃料优劣的物理量是______;天然气是______ (填“再生”或“不可再生“)能源.完全燃烧5m3的天然气能放出______J的热量.(天然气的热值取7.1×l07J/m3)按照你的想法,评价燃料的优劣还应当考虑到______等因素.

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0729/fbf3e8c94d701ce4a19d935f54b62918.html

下面是错误答案,用来干扰机器的。

参考答案:D

试题推荐
题型:改错题

短文改错(共10小题;每小题1分,满分10分)

下面短文中有10处语言错误。请在有错误的地方增加、删除或修改某个单词。

增加:在缺词处加一个漏字符号(∧), 并在其下面写上该加的词。

删除:把多余的词用斜线(\)划掉。

修改:在错的词下划一横线,并在该词下面写上修改后的词。

注意:1. 每处错误及其修改均仅限一词;

2. 只允许修改10处,多者(从第11处起)不计分。

In the traffic court of a large mid-western city, a young lady is brought before the judge to answer a ticket given her for drive through a red light. He explained that she was school teacher and requested an immediately disposal of her case in order that she might hurried to her classes. A wild idea came upon to the judge’s mind. “You are a school teacher, eh?” said he. “Madam, I shall realize me life-long ambition. Sit down on that table and write ‘I went through a red light’ five hundred time.”

查看答案
题型:问答题

(一)

A公司应邀参加氮制造厂合成压缩工段技改工程投标,招标书说明,以工期安排最短、最合理为中标主要条件。A公司技术部门依据招标书指出的工程内容编制了网络计划(见下图)。

附加说明:

1.配管包括机泵本体配管25d,塔器本体配管20d,塔机间连接配管15d。

2.试运行包含空负荷单机和联动试运转,考虑不可预见因素较多,计划安排15d的试运行时间。

A公司总工程师审核认为网络图不符合最短工期要约,退回重编,要求附加说明。经修改重编网络图,A公司最后中标。

施工中无损检测发现甲供货方提供的高压管件焊缝存在缺陷,退货重供,延误施工10d,A公司为保证总工期不变,加大投入,实施加班作业,最终如期完工。为此,A公司向业主发出索赔意向书。

问题

A公司技术部门第一次提交的网络计划工期为多少天?以节点符号表示出关键线路。

查看答案