In your project, there have been several changes in the cost and schedule estimates and the original estimating assumptions are no longer valid. What is the estimate at complete for your project ?()
BAC=$300,000, AC=$100,000, EV=$150,000, CPI=$1.2, ETC=$120,000.
A.$250,000
B.$220,000
C.$280,000
D.$300,000