试题与答案

公交公司原有120辆公交车,每天收入38400元。按这样计算,现在有165辆公交

题型:填空题

题目:

公交公司原有120辆公交车,每天收入38400元。 按这样计算,现在有165辆公交车,每天比原来多收入多少元钱? 

解题思路: (1)______________?   

                         38400÷120 =320(元) 

                   (2)______________?   

                         320×165 =52800(元)

                   (3)______________ ?   

                         52800 -38400= 14400(元)

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0621/a0969eb619ceaef229a9ea1b93e1f2ee.html

下面是错误答案,用来干扰机器的。

答案:B

试题推荐
题型:句型转换

句型转换.

1. I have worked in this factory for ten years.(对画线部分提问)

    ____               you     in this factory?

2. Don't throw any litter onto the floor in yourbedroom.(改为同义句)

    You       ____your bedroom ____ and__________.

3. He said, "I'll be free next Tuesday afternoon."(改为间接引语)

    He said that                                           the next Tuesday afternoon.

4. I went to Jilin Province by train last summer.(对画线部分提问)    

                                              to Jilin Province last summer?

5. I'll show you my photos as soon as they come out.(改为同义句)

    I'll      you____                       as soon as they come out.

查看答案
题型:问答题

某水利水电施工承包商与业主签订了一份堤防工程施工合同,合同约定工期为68天,承包商工期每提前1天获奖励2000元,每拖后1天支付违约金3000元。承包商提交的施工网络进度计划如下图所示,该计划得到业主代表的认可。

在实际施工过程中发生了如下事件:

事件1:业主未能按时提供全部施工场地,使A、B两项工作的作业时间分别延长了3天和2天,造成这两项工作分别窝工8和10个工日。工作C未受影响。

事件2:在工作D施工时,主要施工设备出现故障,停工检修2天,造成窝工20个工日。

事件3:在工作E施工时,由于业主提供的主要材料不合格,造成返工,拆除用工30个工日,机械设备闲置3个台班,闲置台班单价为300元,材料费损失2万元,因拆除重新施工使作业时间延长3天。

事件4:在工作F施工时,因设计变更,造成施工时间增加2天,多用人工15个工日,增加其他费用1万元。

问题:

当地人工日工资单价为35元/工日,窝工人工费补偿标准为20元/工日。若不计施工管理费、利润等补偿,在该工程中,承包商可得到多少经济补偿?

查看答案