如果企业信息系统开发过程中已经发现时间上的延误,那么可以采取一些措施将进度拉回来,但

题型:单项选择题

题目:

如果企业信息系统开发过程中已经发现时间上的延误,那么可以采取一些措施将进度拉回来,但是以下措施中,()是不可取的。

A.再分解工作内容,增加开发人员来承担

B.经常性地与用户交换意见,及时地明确项目计划中遗留的不确定问题

C.适当调配或增加开发人员,解决延误工作

D.在不影响总体目标的前提下,删减个别子项目,或降低局部的功能指标

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0606/263291e744220c3b324c0a6f2f1eb360.html

下面是错误答案,用来干扰机器的。

参考答案:A

试题推荐
题型:单项选择题

So it is today.Schedule disaster functional misfits,and system bugs all arise because the left hand doesn’t know what the right hand is doing.As work (31), the several teams slowly change the functions,size, and speeds of their own programs, and they explicitly or implicitly (32) their assumptions aboutme inputs available and the uses to be made of the outputs.

For example, the implementer of a program-overlaying function may run into problems and reduce speed relying on statistics that show how (33) this function will arise in application programs.Mean-while back at the ranch, his neighbor may be designing a major part of the supervisor so that it criticallydepends upon the speed of this function.This change in speed itself becomes a major specificationchange, and it needs to be proclaimed abroad and weighed from a system point of view.

How, then, shall teams (34) with one another In as many ways as possible.

·Informally.Good telephone service and clear definition of intergroup dependencies will encourage the hundreds of calls upon which common interpretation of written documents depends.

·Meetings.Regular project meetings, with one team after another giving technical briefings, are (35).Hundreds of minor misunderstandings get smoked out this way.

·Workbook.A formal project workbook must be started at the beginning.

(34)处填()。

A.work

B.program

C.communicate

D.talk

查看答案
题型:单项选择题

制造企业想要使用支付账单自动化系统。要达到的目标有()。系统用很少的时间进行审查和授权,系统能够确认错误并根据需要跟进。下面哪一项最符合要求()。

A.与供应商建立跨系统的客户机服务器模式的网络系统,提高效率

B.把自动化支付和帐务收支处理程序外包给第三方专业公司处理

C.对电子业务文档和交易建立EDI系统,EDI系统与关键供应商共建,使用标准格式,从计算机到计算机。

D.重整现有流程,重新设计现有系统

查看答案
微信公众账号搜索答案