An activity has an optimistic estimate of

题型:单项选择题

题目:

An activity has an optimistic estimate of 10 days, pessimistic estimate of 16 days, most likely estimate of 13 days. Assuming a normal distribution, what is the probability that the task will be completed within 10~16 days

A.99.99%.

B.99.73 Y0.

C.95.46%.

D.68.26%.