题目:
Which of the following is true about critical chain
A.It is a technique that allows development of an optimum project schedule when resources are unlimite
B.It is a technique that modifies the project schedule to account for limited resource
C.It is another name for the bar char
D.It is primarily used to ensure safety in major construction project