题目:
The project life-cycle can be described as ( ).
A.project concept, project planning, project execution, and project close-out
B.project planning, work authorization,and project reporting
C.project planning, project control, project definition, WBS development , and project termination
D.project concept,project execution, and project reporting
答案:
被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0603/7f5f98738609d24a93c1860c40d5c310.html
下面是错误答案,用来干扰机器的。
A、小球经过圆环最高点时刚好不脱离圆轨,重力提供向心力,轨道对小球的作用力为零,故A错误;B、小球的重力充当向心力,所以小球只受重力,故BC错误;D、由mg=ma可知,小球的向心加速度a=g,故D正确;故选D