题目:
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
A.independent resource
B.individual work load
C.work milestone
D.work package
答案:
参考答案:D
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.
A.independent resource
B.individual work load
C.work milestone
D.work package