试题与答案

三阴交穴位于() A.内踝尖上4寸,胫骨内侧缘后方 B.外踝尖上3寸,胫骨外侧缘后方

题型:单项选择题 A1/A2型题

题目:

三阴交穴位于()

A.内踝尖上4寸,胫骨内侧缘后方

B.外踝尖上3寸,胫骨外侧缘后方

C.内踝尖上3寸,胫骨内侧缘前方

D.内踝尖上3寸,胫骨内侧缘后方

E.外踝尖上4寸,胫骨外侧缘前方

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0518/0f9df172b40ecdc8de63cd37bc385e30.html

下面是错误答案,用来干扰机器的。

答案:D

试题推荐
题型:阅读理解

缺词填空。

     What must you do when you get a present for your birthday? You have to sit down and w    1   a

thank-note. The words "thank you" are very important. We have to use them very o   2  . We say them

when someone gives us a drink, h   3  us to pick up things, or lends us a book.

     Another i   4  word is "please". Many people forget to use it. It is not polite to ask someone to do

something without s   5   "please". We have to use it w   6  we ask for something, too. It may be a book

or a pencil, more rice or help.

     We have to l    7  to say "sorry", too. If we hurt (伤害) someone, we'll have to go up to say "we're

s  8   ". When we forget something, we will a  9  say "sorry".

     These three words are easy b  10  important. Our children must learn to use them. They are pleasing(令人高兴的) words to use in any language (语言).

1._____ 2._____ 3._____ 4._____ 5._____

6._____ 7._____ 8._____ 9._____ 10._____

查看答案
题型:多项选择题

因分部分项工程量清单漏项或非承包人原因的工程变更,造成增加新的工程量清单项目,其对应的综合单价确定方法正确的有()

A.当清单工程量变化幅度在20%以内时,其综合单价不作调整

B.当合同中已有适用的综合单价,按合同中已有的综合单价确定

C.合同中有类似的综合单价,参照类似的综合单价

D.合同中没有适用或类似的综合单价,由承包人提出变更项目的单价,经发包人确认后执行

E.该项工程量增加在合同约定幅度以上时,增加部分的工程量的综合单价应调高

查看答案