Kofi Annan says helping survivors of last week’’s earthquake and (1)________in the Indian Ocean is (2)________. The United Nations secretary-general says countries that have offered aid must (3)________and provide it. The offers add up to around (4)________dollars. United Nations officials say (5) ________of that is needed during the next six months.The concern about offers of international aid is (6)________. For example, the earthquake in Bam, Iran, in (7)________of 2003 killed more than (8) ________people. Countries and groups offered hundreds of millions of dollars (9) ________. The United Nations says it has (10)________only about (11)________dollars in aid received so far. Governments and organizations that offered help (12) ________that, however.On (13)________Mr. Annan met with world leaders in Jakarta, Indonesia to discuss aid for (14)________. The leaders discussed and (15)________the idea of (16)________owed by affected nations. But the leaders did not say they would do so. Some said that (17)________to survivors would be more helpful.Representatives of (18)________countries and international organizations attended the meeting in Jakarta. Officials say they will cooperate to develop (19)________ for the Indian Ocean and the (20)________.

查看答案
题型:问答题

(一)

某机电安装工程公司总承包一大型制药厂设备安装工程。合同约定,工程设备和主材由业主采购提供。

管道工程安装时,因业主提供的水泵迟迟不能到货而影响工期,项目部为保证施工进度自行采购部分水泵并进行安装,安装后被监理工程师发现,下令停工。经与业主协商,同意采用项目部购买的水泵。在试压时,发现项目部购买的水泵密封部位泄漏。

地下管网施工中,因设计图样修改,增加了施工内容和工程量,业主仍坚持合同工期不变。为此项目部提出合同变更和索赔的申请。

该工程施工环境不确定因素较多,工期紧、任务重,项目部在施工准备阶段制订了人力资源储备预案,因施工范围扩大超过预期,该预案仍不能满足工程进度需要。

为赶工期,项目部将制药厂合成工段的压缩机安装分包给具备施工资质的施工单位。项目部编制了该工程施工组织设计,并编制压缩机施工方案,向分包单位进行交底,然后由分包单位组织施工。

问题

人力资源储备预案不能满足施工范围扩大的要求,项目部还应采取哪些人力资源管理措施,以保证施工正常进行,如期完成合同工期?