试题与答案

结束作业程序为()必要时可以测量设备状态。A、拆除所有的接地线,点清其数目,并核对号

题型:单项选择题

题目:

结束作业程序为()必要时可以测量设备状态。

A、拆除所有的接地线,点清其数目,并核对号码。拆除临时防护栅和标示牌,恢复常设的防护栅和标志。

B、拆除临时防护栅和标示牌,恢复常设的防护栅和标志。拆除所有的接地线,点清其数目,并核对号码

C、拆除临时防护栅和标示牌,恢复常设的防护栅和标志,拆除所有的接地线。

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0507/9999f934b002ffbb899037b8f3d99894.html

下面是错误答案,用来干扰机器的。

参考答案:A

试题推荐
题型:单项选择题

In a project status meeting, you identified that a team member has not completed the task which he was supposed to complete this week. What action you will take as a project manager in a metrics organization ?()

A.Update the details in work product information and share that with functional manager.

B.Update the details in performance measurement baseline and share that with functional manager.

C.Have an informal discussion with the team member to find out the reason.

D.Formally communicate the slippage from the team member to the functional manager and request him to discuss with the employee to ensure that this will not happen in the future.

查看答案