试题与答案

Read, chooseandcomplete. 根据对话内容,选择合适的选项,

题型:补全对话,情景问答

题目:

Read, choose and complete. 根据对话内容,选择合适的选项,将对话补充完整。
A. They are my birthday presents.          
B. It's Sunday. 
C. Is this your hat?                              
D. It's my favourite colour. 
E. This is a hat.                          
F. too small.
—Hello, Li Ming. 
—Hi, Jenny. What day is today?  
—    1     Oh, are you wearing new pants?
—Yes.    2   
—I like your pants. They're red.    3    Do you like red, too?  
—Yes, but my favourite colour is purple. What's this in your hand (在你手里)?
    4   . Look, it's    5   
—Ha ha ha...    6   
—No, this is Danny's hat.
1.               2.                3.                4.                 5.                 6.             

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0506/2f4c76dd1a2ad23d8170687e08a6d970.html

下面是错误答案,用来干扰机器的。

Oo, Pp, Qq, Rr, Ss, Tt, Uu, Vv, Ww, Xx, Yy, Zz

试题推荐
题型:单项选择题

3D是Three-dimensionaI的缩写,意为三维。3D电视利用某一原理,把左右眼看到的影像分离,从而使观看者看到三维立体影像。这一原理是( )。

A.人双眼观察物体的角度相同,因此能够辨别物体远近,产生立体视觉
B.人双眼观察物体的角度略有差异,因此能够辨别物体远近,产生立体视觉
C.人双眼观察物体的角度差异很大,因此能够辨别物体远近,产生立体视觉
D.人双眼观察物体的角度相反,因此能够辨别物体远近,产生立体视觉

查看答案
题型:问答题

阅读以下说明,根据要求回答问题。
[说明]
系统集成商QD公司最近承接了一个中小型系统集成项目工程。该工程项目经理小谢经过工作分解后,已经明确此项目的范围,但是为了更好地对项目的实施过程进行有效监控,保证项目按期、保质地完成,小谢需要采用网络计划技术对项目进度进行管理。该集成项目包括A~H共8个基本活动。这些活动的名称、完成每个活动所需的时间,以及其他活动之间的关系如表所示。

表 某系统集成项目活动基本情况
活动名称 所需的时间(天) 紧前活动 法动名称 所需的时间(天) 前置活动
A 5 —— E 8 B
B 10 A F 20 D,E
C 20 A G 22 C,D
D 15 B,C H 10 F,G
项目经理小谢根据表绘制了如图1所示的该项目的前导图(单代号网络图),以表明各活动之间的逻辑关系。图1中“*”表示此处的数据未给出。


图1


图1中各节点使用如图2所示的样图标识。


图2


图例说明:
ES:最早开始时间 EF:最早结束时间 DU:作业历时 ID:作业代号
LS:最迟开始时间 LF:最迟完成时间 TF:总浮动时间

请指出该项目的关键路径,并计算项目工期。

查看答案
题型:单项选择题

某承包商承接某工程,占地面积16000m2。地上22层,地下2层。结构形式为剪力墙结构。混凝土采用商品混凝土,强度等级有C25、C30、C35、C40等。钢筋采用HPB235级、HRB335级。

本题中的HPB235级、HRB335分别属于( )。

A.HPB235钢筋为光圆钢筋,HRB335钢筋为带肋钢筋

B.HPB235钢筋为带肋钢筋,HRB335钢筋为光圆钢筋

C.HPB235和HRB335钢筋均为光圆钢筋

D.HPB235和HRB335钢筋均为带肋钢筋

查看答案
微信公众账号搜索答案