题型:单项选择题

题目:

A project management team has subcontracted work to a service company. Which of the following tools is the best choice to assure that this company will be able to meet the quality requirements of the project

A) Quality audit.
B) Deliverable inspection.
C) Fixed price contract.
D) Service level agreement.

答案: