试题与答案

句型转换。 1. TurnofftheTV. (改为否定句) _________

题型:句型转换

题目:

句型转换。

1. Turn off the TV. (改为否定句)

__________________________________________________________     

2. It is rainy today. (对画线部分提问)

__________________________________________________________     

3. I like to make a snowman in winter. (对画线部分提问)

__________________________________________________________      

4. He saw a man in the room. (改为否定句)

__________________________________________________________      

5. I cleaned the house yesterday. (对画线部分提问)

__________________________________________________________ 

答案:

1. Don't turn off the TV.     

2. How is the weather today?      

3. What do you like to do in winter?     

4. He didn't see a man in the room.      

5. When did you clean the house?

试题推荐
题型:综合

图所绘为1941年12月7日日本海空军偷袭美国珍珠港舰队航海路线示意图。用你学过的知识,回答下列问题:(8分)

(1)A处为____________________渔场,是由_____________流和__________流在此汇合而形成。

(2)日本海军选择了M代表的路线,而没有择N路线,那么M路线的有利条件是:

①这条航线航程_________,理由是_____________________________________。

②冬季该路线上空天气特点是_____________________________________。

③这条航线使舰队的航速_______,理由是________________________________。

查看答案
题型:问答题

某工程采用公开招标方式,招标人3月1日在指定媒体上发布了招标公告,3月6日至3月12日发售了招标文件,共有A、B、C、D四家投标人购买了招标文件。在招标文件规定的投标截止日(4月5日)前,四家投标人都递交了投标文件。开标时,投标人D因其投标文件的签署人没有法定代表人的授权委托书而被招标管理机构宣布为无效投标。
该工程评标委员会于4月15日经评标确定投标人A为中标人,并于4月26日向中标人和其他投标人分别发出中标通知书和中标结果通知,同时通知了招标人。
发包人与承包人A于5月10日签订了工程承发包合同,合同约定的不含税合同价为6948万元,工期为300天;合同价中的间接费以直接费为计算基数,间接费率为12%,利润率为5%。
在施工过程中,该工程的关键线路上发生了因以下几种原因引起的工期延误:
(1)由于发包人原因,设计变更后新增一项工程于7月28日至8月7日施工(新增工程款为160万元);另一分项工程的图纸延误导致承包人于8月27日至9月12日停工。
(2)山于承包人原因,原计划于8月5日晨到场的施工机械直到8月26日晨才到场。
(3)由于天气原因,连续多日高温造成供电紧张,该工程所在地区于8月3日至8月5日停电。另外,该地区于8月24日晨至8月28日晚下了特大暴雨。
在发生上述工期延误事件后,承包人A按合同规定的程序向发包人提出了索赔要求。经双方协商一致,除特大暴雨造成的工期延误之外,对其他应予补偿的工期延误事件既补偿直接费又补偿间接费,间接费补偿按合同工期每天平均分摊的间接费计算。

该工程所在地市政府规定,高温期间施工企业每日工作时间减少1小时,企业必须给职工每人每天10元高温津贴。若某分项工程的计划工效为1.50m2/小时,计划工日单价为50元,高温期间的实际工效降低10%,则高温期间该分项工程每m2人工费比原计划增加多少元
(注:费用计算结果保留两位小数)