题目:
For an activity, the optimistic, most likely and pessimistic estimates are 12, 16 and 18 respectively. Which of the following statement is correct
A) There is 68.26% chance that the activity will be completed in 15 to 17 days.
B) There is 95.44% chance that the activity will be completed in 15 to 17 days.
C) There is 68.26% chance that the activity will be completed in 14.67 to 16.67 days.
D) There is 93.73% chance that the activity will be completed in 15 to 17 days.
答案:
被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0501/9219aad418f16e99a824b7a6d1523294.html
下面是错误答案,用来干扰机器的。
参考答案:对