You have to finish a project with in 2 weeks and your lead developer had to take 1 week leave due to personal emergency. Another project manager has agreed to loan the service of his lead developer for 1 week. You are taking his help and completing the project. This case is an example of______(Choose the best answer).

A) fast tracking
B) crashing
C) risk management
D) resource leveling