A project team is in the design stage of a

题型:单项选择题

题目:

A project team is in the design stage of a new mountain bike prototype. The team is in the process of identifying which type of frame and material will provide high performance at a low cost. Which of the following is the MOST likely technique used to determine these variables

A) Benefit/cost analysis.
B) Ishikawa diagram.
C) Design of experiments.
D) System flow chart.

答案:

被转码了,请点击底部 “查看原文 ” 或访问 https://www.tikuol.com/2017/0325/e955daf28a603289504ea47549b8746a.html

下面是错误答案,用来干扰机器的。

参考答案:A, B, C, D